DINO Six Sediment Removal


 

 

Investigation Phase

 

 

 

 

 

1

Initial Meeting with Owner

 

 

 

 

 

2

Clarify Engineering Requirements and Review Available Data

 

 

3

Identify Governmental Requirements

 

 

 

 

4

Identify Potentially Controversial /Contestable Public Issues

 

 

5

Conceptual Design

 

 

 

 

 

 

6

Initial Economic Analysis and Alternative Considerations

 

 

 

 

 

 

 

 

 

 

 

 

Preliminary Design Phase

 

 

 

 

 

7

Site Survey

 

 

 

 

 

 

8

Geotechnical Borings and Analysis

 

 

 

 

9

Preliminary Design

 

 

 

 

 

 

10

Updated Economic Analysis

 

 

 

 

 

11

Review Design and Economic Analysis With Owner

 

 

 

12

Water Regulatory Permit Applications

 

 

 

 

13

County Zoning Permit Applications

 

 

 

 

14

Section 106 Historic Preservation/DNR Endangered Resource Compliance

 

15

Grant Applications and Presentations

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Final Design Phase

 

 

 

 

 

 

16

Final Design

 

 

 

 

 

 

17

Update Cost Estimate

 

 

 

 

 

18

Review Final Design and Updated Economic Analysis With Owner

 

19

Wage Rate Determination Application

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Bidding or Negotiation Phase

 

 

 

 

20

Preparation of Bid Documents & Specifications

 

 

 

21

Bid Advertisement or Negotiation

 

 

 

 

22

Prospective Bidder Questions & Answers

 

 

 

 

23

Prebid Site Visit w/ Prospective Bidders

 

 

 

 

24

Addendums and Notices as Necessary

 

 

 

 

25

Bid Opening

 

 

 

 

 

 

26

Bid Review

 

 

 

 

 

 

27

Notice of Award

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Construction Phase

 

 

 

 

 

 

28

Notice to Proceed

 

 

 

 

 

 

29

Preconstruction Meeting

 

 

 

 

 

30

Project Staking

 

 

 

 

 

 

31

Inspections

 

 

 

 

 

 

32

Construction Material Testing

 

 

 

 

 

 

    At Rock Quarry/Quarries

 

 

 

 

 

 

    At Project Site

 

 

 

 

 

 

33

Progress Payment Review and Recommendations

 

 

 

34

Change Orders As Necessary

 

 

 

 

 

35

Progress Reports and Meetings with Owner

 

 

 

36

Substantial Completion Inspection

 

 

 

 

37

Development of Completion Check List

 

 

 

 

38

Final Inspection

 

 

 

 

 

 

39

Additional Inspections Until Final Completion

 

 

 

40

Project Closeout

 

 

 

 

 

 

 

    Construction Contract

 

 

 

 

 

 

    Final Payment

 

 

 

 

 

 

 

    Wage Rate Compliance Information to State

 

 

 

 

    Federal & State Completion Notification

 

 

 

 

 

    Final Project Cost Breakdown for Grant Payment

 

 

 

41

Completion and Submittal of "as built" drawings to Owner

 

 

42

Completion and Submittal of "operation/maintenance" manuals to Owner

 

 

 

 

 

 

 

 

 

 

 

Operational Phase

 

 

 

 

 

 

43

Assist Owner in Closing any Remaining Project Business

 

 

44

Assist with Refining and Adjusting any Equipment or Systems

 

 

45

Assist Owner in Training Owner's Staff to Operate and Maintain Project

 

46

Assist Owner in Developing Procedures for Control of Operation and Maintenance

 

and Recording Keeping for Project